Points/Hours System Estimation

Purpose and Scope

This SOP outlines how to estimate development efforts using points (for Bubble/FlutterFlow) or hours (for Glide/Webflow). The goal is to ensure consistent and transparent time estimations, enabling accurate client quotes and project planning.

Client Estimates: Always convert points to hours by applying the appropriate multiplier:

  • Base multiplier: total points ×2

  • If task includes both design and QA: total points ×3

Client-facing estimates must always be in hours.


Definitions

Point System: A method to estimate tasks using points (Bubble/FlutterFlow only).

Scale:

  • 1 point = 1–3 hours (less than half a day)

  • 2 points = 4 hours (half a day)

  • 3 points = 8 hours (1 workday)

Client Conversion: 

  • Default: Total points ×2 = Client hours

  • With design and QA: Total points ×3 = Client hours
    (e.g., 3 points with design and QA = 9 client hours)

Development Tasks: Work requiring software creation/modification (front-end, back-end, integration).

PM: Project Manager overseeing timelines and resource allocation.


Procedure

  1. Assess Task Requirements

    • Break down tasks into components (front-end, back-end, testing, etc.).

    • Flag incomplete scopes or dependencies to the PM.

  2. Assign Dev Points/Ranges

    For Bubble/FlutterFlow:

    • Assign a point range (e.g., 3–5 points).

    • Include testing/QA time in points.

    Example:

    mathematica
    Front-End: 1–2 points Back-End: 1–2 points Testing: 1 point Total: 3–5 points → Client estimate = 6–10 hours (or 9–15 hours if includes design and QA)

    For Glide/Webflow: Estimate directly in hours (no points).

    Always: Overestimate rather than underestimate.

  3. Add Estimates to Task

    • Input points/hours in the task’s custom field.

    • For Points: Add a comment with the client hour conversion (e.g., “3–5 points = 6–10 client hours” or “3–5 points = 9–15 client hours (includes design + QA)”).

  4. Tag the PM

    • Notify the PM in the task comments (e.g., “@PM – Dev points added: 3–5 points (9–15 client hours including design + QA)”).


Example Scenario

Task: Build a user dashboard (Bubble).

Estimates:

  • Front-End: 2–3 points

  • Back-End: 1–2 points

  • Testing: 1 point

  • Total Points: 4–6

Client Hours:

  • Default: 8–12 hours

  • With Design + QA: 12–18 hours

Communication:
“@PM – Dashboard task: 4–6 points (12–18 client hours including design + QA). Testing included.”


Best Practices

Transparent Client Communication:

  • Never share internal points with clients—always use hours.

  • Explain hourly ranges to clients (e.g., “This feature will take 12–18 hours”).

Collaboration:

  • Discuss uncertainties with the PM before finalizing estimates.

Documentation:

  • Record assumptions (e.g., “Testing assumes no major back-end bugs”).


Key Considerations

  • Double-Check Multipliers: Ensure the right multiplier (×2 or ×3) is used for client hours.

  • Buffer for Complexity: Add 10–20% extra hours for ambiguous tasks.

  • Feedback Loop: Review past estimates to improve accuracy.